Puławy court and prosecutor’s office expansion underway
Puławy court expansion begins demolition and relocations; the project will add nearly 2,000 sqm and finish in 2028.
Puławy court expansion has entered an active demolition phase, and locals see construction behind tall fencing between the Town Hall and the Garnisonowy church. Consequently, crews remove old fittings, windows and parts of the façade while the building awaits a new form.
Puławy court expansion: what will change
Workers will raise the lower, ground-floor wing by two storeys to match the taller side. Therefore the court and the prosecutor’s office will gain almost two thousand square metres of usable space. Moreover, the refurbishment will add an elevator, separate staircases for staff and visitors, modern HVAC and more spacious hearing rooms. However, officials have not published any detailed visualisations. In addition, project notes say the renewed walls will use a grey colour scheme.
Work, contractor and timeline
The Lublin Court of Appeal commissioned the upgrade, and Baudziedzic from Głogów Małopolski won the contract. Consequently, the firm will receive more than PLN 57 million for the construction. Moreover, the schedule foresees completion in 2028. Meanwhile, crews continue demolition and dismantling of old installations. Therefore residents should expect noise and delivery traffic for the next two years.
Temporary relocations and how services continue
Because of the works, the court and prosecutor’s staff moved into several nearby buildings. For example, the court’s filing office, civil department, family and minors department, labour department, probation team and records reading room now operate at al. Partyzantów 6A. Meanwhile, the criminal department and enforcement section moved to the Science and Technology Park at ul. Mościckiego 1. In addition, the entire District Prosecutor’s Office occupies space at that address. Furthermore, the land and mortgages department and court leadership offices sit at Lubelska 6A.
Regional context and broader implications
Puławy joins a regional trend of upgrading county courthouses across the Lublin region. For instance, new or expanded sites opened in Opole Lubelskie and Janów Lubelski in recent years. Consequently, the upgrades aim to modernise workflows and improve access to justice. Moreover, better buildings usually mean more space for public counters and secure rooms. Therefore people with legal matters should benefit from clearer pathways and more privacy during hearings.
Finally, the project aims to modernise the city’s judicial infrastructure while preserving public access to services. However, residents and expats should monitor announcements about service moves and planned hearings. Consequently, the reconstruction will change how people meet the justice system in Puławy for years to come.
Source: Read original article