Probe into Sosnowica sewage plant contract
Investigation into the Sosnowica sewage plant contract exposes alleged corruption and procurement failures that affect public funds and local services.
The police and prosecutors have closed in on a controversial project after a probe found alleged procurement breaches tied to the Sosnowica sewage plant. Consequently, investigators now accuse the former mayor of exceeding his powers and breaching public procurement rules.
Sosnowica sewage plant: what prosecutors say
Investigators finished gathering evidence, and the case now nears completion. Moreover, they interviewed witnesses and secured documents. In addition, they obtained an expert opinion on public procurement law. Therefore, prosecutors charged the former mayor with overstepping his authority. However, the most serious claim alleges he sought personal gain through the choice of contractor.
How the tender went wrong
Prosecutors say the tender flaws date to 2022. The former mayor failed to define duties for the tender committee. In addition, he omitted key exclusion criteria from the announcement. Consequently, the rules lacked transparency. Moreover, the winning bid contained gaps. For instance, it missed a required price breakdown. However, the committee did not reject that bid. Therefore, the prosecutor argues the decision harmed the public interest.
Political fallout and local administration
The dispute surfaced after new local leaders took office in 2024. The new mayor ordered an audit and then terminated the contract. In addition, he notified prosecutors. However, the council fractured over the move. Some councillors sided with the contractor. Consequently, they questioned the decision to go to court. Moreover, they warned that funding could be lost. In the end, the funding promise extended and the municipality now plans a new tender.
Meanwhile, the municipality runs a legal fight with the previous contractor. The contractor claims the termination lacked grounds. Therefore, the case may lengthen project delays. In addition, the council says it will redesign the plan to allow trucked sewage. This change aims to help households that use cesspools.
Local impact and public services
The case matters beyond local politics. Firstly, it affects water quality and public health. Secondly, it could shape residents’ costs for sewage services. In addition, stalled work may delay EU or national funds. Moreover, long procurement disputes raise legal and financial risks for the municipality. Therefore, taxpayers and property owners should pay attention.
The former mayor denies wrongdoing. However, the charges carry up to ten years in prison if proven. Investigators plan to close the case in April. Therefore, the municipality aims to relaunch procurement and to secure services for residents soon.
Source: Read original article